Regional Affordable Housing Bond
On November 6, 2018, voters approved Measure 26-199 and Oregon Measure 102. These measures provide $652.8 million in resources to the Portland metropolitan region for affordable housing development and allow the funds to be leveraged with additional resources and partnerships.
Washington County jurisdictions received $192.2 million of the total bond funds, and they were divided up between Washington County ($118.9 million), the City of Beaverton ($31.8 million) and the City of Hillsboro ($41.5 million).
Washington County is using these funds to build high quality, affordable homes that will serve our community for decades to come.We are on track to exceed our production goals, increasing accessible housing for households with very low-incomes, families who need larger units, and those who need additional supports to maintain housing stability.
Project Goals
Progress Map
Housing Projects funded with Metro bond
Status: Completed
Click the name of any project below to view full details. For an inside look into the different projects, such as their ground breakings and grand openings, please visit our project playlist here.
Key | Project | Location | Completion Date | Units |
---|---|---|---|---|
1 | The Viewfinder | Tigard | December 2021 | 81 |
2 | The Valfre at Avenida 26 | Forest Grove | July 2022 | 36 |
3 | Heartwood Commons | Aloha | March 2023 | 54 |
4 | Terrace Glen | Tigard | May 2023 | 144 |
5 | Alongside Senior Housing | Tigard | September 2023 | 57 |
6 | Cedar Rising | Aloha | December 2023 | 81 |
7 | The Opal | Cedar Mill | March 2024 | 54 |
8 | Plaza Los Amigos | Cornelius | May 2024 | 112 |
9 | Altura | Beaverton | August 2024 | 74 |
Status: Under Construction
Key | Project | Location | Completion Date | Units |
---|---|---|---|---|
10 | Plambeck Gardens | Tualatin | January 2025 | 116 |
Status: In Planning
Key | Project | Location | Completion Date | Units |
---|---|---|---|---|
11 | Woodland Hearth | Tigard | April 2026 | 63 |
12 | 209th Ave | Aloha | Fall/Winter 2027 | 86 |
Plans and Reports
- Local Implementation Strategy
The guiding principles of the Local Implementation Strategy are:
- Housing Development plan including criteria and selection process for projects
- Strategy for advancing racial equity throughout implementation
- Engagement reports summarizing how stakeholder input and community outreach shaped development of the strategy (see page 33 of the Local Implementation Strategy)
- Plan for ongoing community engagement
The final version of Washington County's Local Implementation Strategy was approved by the Board of County Commissioners on December 17, 2019.
- Annual Reports
- Project Summaries