We will design a replacement bridge for 205th Avenue at Beaverton Creek.
We will begin with a traffic analysis to determine if the road needs to be widened to three lanes (one motor vehicle travel lane in each direction and a center turn lane) or five lanes (two motor vehicle lanes in each direction with a center turn lane).
Additional improvements include:
- Bike lanes
- Sidewalks
- Retaining walls
- Guardrails
- Street lights
- Improved storm drainage
- Storm water treatment facilities
Design start: September 2022
Design finish (expected): January 2026
Construction start (expected): Spring/summer 2026
Construction finish (expected): Fall 2027
Sign up to receive project updates by email
Update
11/22/2024: Comment on two design alternatives for bike and pedestrian facilities at an online open house, Nov. 22-Dec. 8.
Funding
Cost Estimate: $22.7 million
Funding sources:
- Major Streets Transportation Improvement Program (MSTIP 3e, MSTIP 3f)
- Transportation Development Tax