We will add a signalized pedestrian crossing with push-buttons, street lights and ADA-compliant ramps to improve pedestrian safety.
The signal is a High-intensity Activated Crosswalk (HAWK), which stops drivers with a red light and allows pedestrians to cross. See how to use a HAWK.
We are doing this project at the same time as the Florence Street sidewalk project.
Construction start (expected): May 2023
Construction finish (expected): April 2024
Update
4/22/2023: This project is complete.
Funding
Cost: $542,000 (2020 estimate)
Funding sources:
Prior events and comment opportunities
Online open house: June 28-July 14, 2021
Online open house: Dec. 7-20, 2020
Contact(s)