Skip to main content

Florence Street (FY 2020-21 Pedestrian & Biking Improvement)

Florence Street needs sidewalks between 165th and 175th avenues.

We plan to build sidewalks on Florence Street, alternating between the north and south sides of the road, and to install/upgrade streetlights at the intersections.

We will also install or upgrade existing streetlights at the 175th, 173rd and 165th avenue intersections. ADA-compliant curb ramps will be included.

This project is being done at the same time as the 170th Avenue (FY 2020-22 Pedestrian Improvement) project, since the projects intersect.

Construction start (expected): May 2023
Construction finish (expected): April 2024

Update

4/22/2023: This project is complete.

Funding

Cost: $1.1 million (2020 estimate)

Funding source:

Prior events and comment opportunities

Online open house: June 28-July 14, 2021

Online open house: Dec. 7-20, 2020

Contact(s)