We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.
Other improvements include updated:
- Street lighting
- Traffic signs
- Striping
- Storm drainage
- Water quality facilities
Design start: October 2022
Design finish (expected): August 2025
Start right-of-way acquisition (expected): August 2025
Construction start (expected): November 2026
Construction finish (expected): December 2027
Sign up to receive project updates by email
Update
12/31/2024: Design is progressing. We are planning an open house for the spring.
Funding
Cost Estimate: $6.3 million
Funding sources:
- MSTIP Bonding Cost-sharing Program
- Bonny Slope West System Development Charge
Prior events and comment opportunities