We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.
Other improvements include updated:
- Street lighting
- Traffic signs
- Striping
- Storm drainage
- Water quality facilities
Design start: October 2022
Design finish (expected): June 2026
Start right-of-way acquisition (expected): September 2025
Construction start (expected): September 2026
Construction finish (expected): December 2027
Sign up to receive project updates by email(Link is external)
Update
3/21/2025: New date!
Talk with the design team at an open house from 5-7 p.m. Monday, April 14, at Cedar Mill Library, 1080 NW Saltzman Road.
Funding
Cost Estimate: $8.6 million
Funding sources:
- MSTIP Bonding Cost-sharing Program
- Bonny Slope West System Development Charge