Stringtown Road Bridge Replacement

We will replace the Stringtown Road bridge over Prickett Creek. A road closure is required.

The Stringtown Road bridge over Prickett Creek was made of timber and was reaching the end of its usefulness. We replaced the bridge, between Sylvia Lane and Prickett Road, with a concrete open-bottom box culvert. The road was closed during construction.

Construction start: July 29, 2024
Construction finish: October 29, 2024

Sign up to receive project updates by email

Update

10/29/2024: Stringtown Road is open. Project is significantly complete, 27 days ahead of schedule.

Funding

Cost Estimate: $1.8 million

Funding sources: