Skip to main content

South Road Bridge Replacement

We will replace the South Road bridge over the Upper Tualatin River.

We are replacing the South Road bridge over the upper Tualatin River.

The wooden bridge was built in 1974. It is showing sides of decay and needs to be replaced for safety.

South Road will close during construction.

Construction start: August 2024
Construction finish (expected): February 2025

Sign up to receive project updates by email

Update

9/20/2024: South Road is closed at the bridge over the Upper Tualatin River, between Cherry Grove Drive and Mt. Richmond Road through Dec. 9 for bridge replacement. Use Patton Valley Road detour.

Excavation for the new bridge is nearly complete; pile installation is expected to start Oct. 7. Once the piles are in place, the contractor will form and pour the concrete of the bridge ends and walls. Bridge girders are expected to be delivered in late November.

This project is managed by the Oregon Department of Transportation (ODOT).

Funding

Cost Estimate: $861,000

Funding sources:

  • ODOT federal/state funds
  • County Road Fund

Contact(s)