Roy Rogers Road runs north and south and carries 18,000 vehicles per day. Traffic is expected to increase with residential development in the area.
We are widening Roy Rogers Road, between Borchers Drive and Chicken Creek bridge, to improve safety and traffic flow. This will include:
- Five travel lanes, two in each direction and a center-turn lane
- Bike lanes
- Sidewalks
- Storm drainage improvements
- Street lights
- Sound walls
We are partnering on this project with Willamette Water Supply System's new 66-inch drinking water pipeline installation.
Construction start: July 2022
Construction finish: October 2024
Sign up to receive project updates by email
Update
9/6/2024: Construction is substantially complete. There may be intermittent lane closures for corrective work.
Also see:
Tualatin-Sherwood Road Highway 99W Crossing
Tualatin-Sherwood Road (Langer Farms Parkway to Teton Avenue)
CPO 5 (inactive)
Commissioner District 3
Funding
Cost Estimate: $23.3 million
Funding sources:
- Transportation Development Tax
- Willamette Water Supply System reimbursements
- City of Sherwood
Sound walls
The sound walls will be colored concrete.
Prior events and comment opportunities
Online open house June 24-July 15, 2022
Online open house May 8-24, 2020
Open house Aug. 21, 2019:
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services
|