We will rebuild the roadway through a process called full depth reclamation. Full depth reclamation is a process that crushes roadways that have reached the end of their life cycle. The materials are recycled on-site to rebuild strong, cost-effective roads.
Work will result in two, two-week road closures. The first closure will be south of the entrance to the Pumpkin Ridge Golf Club. The second will be north of the entrance. Signed detours around the closures will be provided.
Construction start (expected): June 2025
Construction finish (expected): June 2025
Update
10/11/2024: This project has been postponed until June 2025 due to weather. Full depth reclamation must be completed in dry conditions.
Funding
Cost: $1.2 million
Funding sources: