A culvert on Marsh Road is in poor condition and is too small. It is near milepost 0.3, north of Verboort Road. We will replace the culvert with a larger one that will improve water flow.
Marsh Road will remain open during construction with lane closures.
Construction start (expected): October 10, 2022
Construction finish (expected): November 2, 2022
CPO: 4
Commissioner District: 10
Update 10/26/2022:
This project is complete.
Funding
Cost: $230,000.
Funding source:
![Marsh Road culvert replacement project Map](https://s3.us-west-2.amazonaws.com/washingtoncountyor.gov/styles/max_1300/s3/2022-08/MarshRdCulvert-map.jpg?VersionId=hI9LMHcc0JIaWPsIXdzekOX3fCCZ3.lZ&itok=Jr_WCmvk)
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Road Maintenance |