A small culvert on Jacktown Road is in poor condition and causing damage to the road. This culvert is between Rosedale Road and Farmington Road near milepost 1. We will replace the culvert with a larger concrete box culvert. This will be better for water flow and improve upstream fish passage.
Jacktown Road will be closed during construction.
Construction start (expected): Sept. 26, 2022
Construction finish (expected): Oct. 21, 2022
Update 10/20/2022
This project is complete.
Funding
Cost: $359,000.
Funding source: