We will add sidewalks along the east side of Huntington Avenue between Cedar Hills Boulevard and Glenhaven Street. This sidewalk will connect pedestrians to Cedar Hills Park and William Walker Elementary School.
The Urban Road Maintenance District Advisory Committee voted to change the scope of this project in June 2023. Sidewalk will only be constructed on the east side of Huntington Avenue.
Construction start (expected): October 21, 2024
Construction finish (expected): December 20, 2024
Update
11/25/2024: Construction is underway. Intermittent lane closures are possible.
Funding
Cost: $1,673,000 (2021 estimate)
Funding sources:
Prior events and comment opportunities
Updated Design Map: Sept. 11, 2023
Open House: Feb. 7, 2023
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services
|