There have been repeated road and shoulder failures where it crosses Chicken Creek and West Fork Chicken Creek.
We plan to replace the two culverts with reinforced concrete box culverts and widen the road at this location. This will improve stability of the road base and improve water flow and fish passage.
Construction start (expected): August 26, 2024
Construction finish (expected): October 25, 2024
Update
11/21/2024: Striping work is finished. This project is complete.
Funding
Cost: $900,000 (estimate)
Funding source: