Division Street Culvert Replacement

This project replaced two undersized culverts on Division Street between 149th Avenue and 150th Court.

The two culverts caused flooding in the past. We replaced them with a single larger culvert. This improved water flow and fish passage upstream.

Due to the unique design constraints at the project site, we used an aluminum box culvert instead of concrete to control it's weight and size.

Construction start: August 7, 2023

Construction finish: Sept. 20, 2023

Update

9/22/2023: This project is complete and ​​​​​Division Street has reopened to traffic.

CPO: 6
Commissioner District: 1

Funding

Cost: $530,000

Funding source:

Road Fund