Cornell Road is being improved between 102nd and 113th avenues. Construction began in 2022.

We widened Cornell Road to three lanes, one lane in each direction with a center turn lane, between 102nd and 113th avenues. These improvements address bike and pedestrian safety and traffic flow.

We also installed a traffic signal at the Cornell Road and 107th Avenue intersection. Additional improvements include continuous sidewalk and bicycle facilities, street lighting and storm drainage upgrades.

Construction start: Feb. 15, 2022
Construction finish: August 2023

Sign up to receive project updates by email

Update

10/16/2023: Construction is complete.

Funding

Cost Estimate: $12.9 million