Skip to main content

Bonita Road and Sequoia Parkway Intersection

We are adding a traffic signal to the Bonita Road and Sequoia Parkway intersection.

The Bonita Road and Sequoia Boulevard intersection, near I-5, is a busy intersection in Tigard. We will install a traffic signal to improve safety and traffic flow.

Other improvements include:

  • Crosswalks
  • ADA-compliant curb ramps
  • Some storm drain updates

Design start: June 2024
Construction start (expected): Summer 2026
Construction finish (expected): Winter 2026-27

Update

6/24/2024: Design has started.

Funding

Cost estimate: $1.2 million

Funding source: Major Streets Transportation Improvement Program (MSTIP 3e)

Contact(s)

Contact Us

Transportation Improvement Projects

Phone

503-846-7800