We will improve Blanton Street, between 198th and 209th avenue, with:
- Bike lanes
- Sidewalks
- Street lighting
- Storm water drainage
- Updating striping and signs
The design will match completed improvements west of 209th Avenue.
Construction start (expected): Spring 2025
Construction finish (expected): Winter 2025
Update
9/6/2024: Design is nearing completion. Right-of-way acquisition is starting. Construction is delayed to complete the right-of-way and contractor hiring process.
Funding
Cost Estimate: $5.9 million
Funding sources:
- MSTIP Bonding Cost-sharing Program
- City of Hillsboro
Prior events and comment opportunities
Contact(s)