Alexander Street is in unincorporated Aloha, north of TV Highway. Design options recommended in Aloha Tomorrow Final Report included:
- Improve Alexander Street with two uniform vehicle lanes
- Install alternate parallel parking and landscaping on both sides of the street.
- Build bike lanes and sidewalks
- Upgrade stormwater drainage
- Install a bike/pedestrian signal at the 185th Avenue and Alexander Street intersection

Design start: Summer 2022
Design finish (expected): Summer 2026
Construction start (expected):Fall 2026
Construction finish (expected): Fall 2027
Sign up to receive project updates by email(Link is external)
Update
3/21/2025: We are preparing an open house, tentatively scheduled for April.
Funding
Cost Estimate: $25 million
Funding source : Major Streets Transportation Improvement Program (MSTIP)
Prior events and comment opportunities
Design Update: Dec. 1-18, 2023(Link is external)