We widened 198th Avenue to three lanes, one lane in each direction and a center turn lane.
Additional improvements included:
- Installing continuous bicycle lanes and sidewalks
- Replacing bridges at Butternut and Celebrity creeks
- Improving safety at all intersections
- Upgrading street lighting
- Upgrading storm water treatment
- Improving culvert crossings
Construction start (expected): 5/24/2019
Construction finish (expected): 9/13/2021
Update 10/13/2021
Project is substantially complete.
Funding
Cost: Estimated at $24 million
Funding sources:
- Major Streets Transportation Improvement Program (MSTIP 3d and 3e)
- MSTIP Bonding Cost-sharing Program
- Utility reimbursements
Newsletters
- September 2020
- July 2020
- April 2020
- February 2020
- December 2019
- October 2019
- September 2019
- August 2019
- June 2019
- March 2019
- December 2017
- May 2016
Prior events and comment opportunities
Open House #5 - April 4, 2019
Open House #4 - Dec. 6, 2017
Open House #3 - Nov. 17, 2016
Open House #2 - June 2, 2016
Open House #1 - Dec. 11, 2015
Interested Parties Group Meetings
IPG Meeting #6 - Oct. 20, 2016
IPG Meeting #5 - June 16, 2016
IPG Meeting #4 - May 19, 2016
IPG Meeting #3 - April 14, 2016
IPG Meeting #2 - March 17, 2016
IPG Meeting # 1 - Feb. 18, 2016