Skip to main content

Spring Hill Road bridge construction begins July 10

Construction on the Spring Hill Road bridge at the Tualatin River Overflow is scheduled to start July 10, and will include a three-month road closure beginning July 17.
Media release

For Immediate Release: Monday, July 03, 2017

Sponsored by: Department of Land Use and Transportation, Capital Project Services Division

Construction on the Spring Hill Road bridge at the Tualatin River Overflow is scheduled to start July 10, and will include a three-month road closure beginning July 17.

Traffic will be detoured onto SW Fern Hill Road and Tualatin Valley Highway/OR 47. (See map)

The existing wooden bridge, located south of Highway 47, will be removed once the road is closed. It will be replaced with a wider concrete bridge. The $3.1 million project is funded through the County's Major Streets Transportation Improvement Program (MSTIP) Phase 3d.

For more information about this project, visit the project page or contact Washington County Department of Land Use &Transportation at [email protected] or 503-846-7800. For the latest road construction schedules, visit www.wc-roads.com .

Washington County is committed to planning, building and maintaining a great transportation system, ensuring the safety of all roadway users, and operating the County roadway system in a cost-effective and environmentally responsible manner.

Media Contact:

Melissa De Lyser, Communications Coordinator
503-846-4963
[email protected]