Posted
For Immediate Release: Thursday, September 17, 2020
SW Dober Road, between Iowa Hill and Riedweg roads, will close Sept. 21-Oct. 11 for culvert installation.
The project, originally scheduled to begin Sept. 14, was delayed due to wildfire and poor air quality causing unsafe conditions for crews.
The existing bridge will be replaced with a reinforced concrete box culvert of similar size. The box culvert is designed to meet fish passage requirements.
For more information, visit the project webpage or contact the Washington County Department of Land Use & Transportation at [email protected] or 503-846-ROAD (7623). For the latest road construction schedules, visit www.wc-roads.com.
Washington County is committed to planning, building and maintaining a great transportation system, ensuring the safety of all roadway users, and operating the County roadway system in a cost-effective and environmentally responsible manner.
Media Contact:
Cindy Remy, Senior Communication Specialist/PIO503-846-7696