For Immediate Release: Tuesday, February 17, 2015
Updated paving scheduleUPDATED: 03/06/2015
Due to unforeseen circumstances, paving has been delayed on all remaining projects.
Updated paving schedule as of March 6:
- Tongue Lane (Highway 219 to Iowa Hill): paving will continue through March 9
- Farmington Road (209th to Highway 219): March 16 - 24 (excluding weekend days)
- Old Highway 47 (Scoggins Valley to 835 feet south): March 30 - April 7
- Scoggins Valley Road (Highway 47 to West Shore): March 30 - April 7
- Walker Road (VonNeumann to 185th): May 6 - 7
Paving dates are subject to change due to weather and/or other unforeseen circumstances. This page will be updated if dates change.
Updated paving schedule as of February 17:
- Tongue Lane (Highway 219 to Iowa Hill): March 2 - 5
- Farmington Road (209th to Highway 219): March 9 - 17 (excluding weekend)
- Old Highway 47 (Scoggins Valley to 835 feet south): March 23 - 31
- Scoggins Valley Road (Highway 47 to West Shore): March 23 - 31
Updated paving schedule as of October 31:
- Farmington Road (209th to Highway 219): November 7 - 17 (excluding weekend)
- Tongue Lane (Highway 219 to Iowa Hill): November 17 - 20
- Old Highway 47 (Scoggins Valley to 835 feet south): February-March 2015
- Scoggins Valley Road (Highway 47 to West Shore): February-March 2015
- Walker Road (VonNeumann to 185th): April 2015
Updated paving schedule as of October 24:
- Farmington Road (209th to Highway 219): November 3 - 12 (excluding weekend)
- Tongue Lane (Highway 219 to Iowa Hill): November 10 - 14
- Old Highway 47 (Scoggins Valley to 835 feet south): November 10 - 19 (excluding weekend)
- Scoggins Valley Road (Highway 47 to West Shore): November 10 - 19 (excluding weekend)
- Walker Road (VonNeumann to 185th): April 2015
Updated paving schedule as of October 17:
-
Farmington Road (209th to Highway 219): October 24 - November 4 (excluding weekend)
-
Tongue Lane (Highway 219 to Iowa Hill): November 3 - 6
-
Old Highway 47 (Scoggins Valley to 835 feet south): November 10 - 19 (excluding weekend)
-
Scoggins Valley Road (Highway 47 to West Shore): November 10 - 19 (excluding weekend)
-
Walker Road (VonNeumann to 185th): April 2015
Updated paving schedule as of October 10:
- Farmington Road (209th to Highway 219): October 17, 20 - 24, 27 - 28
- Tongue Lane (Highway 219 to Iowa Hill): October 27 - 31
- Old Highway 47 (Scoggins Valley to 835 feet south): November 3 - 7, 10 - 12
- Scoggins Valley Road (Highway 47 to West Shore): November 3 - 7, 10 - 12
- Walker Road (VonNeumann to 185th): April 2015
Updated paving schedule as of September 26:
- Alexander Street (185th to 209th): September 29 - October 2
- Farmington Road (209th to Highway 219): October 3, 6 – 10, 13 – 14
- Tongue Lane (Highway 219 to Iowa Hill): October 13 - 16
- Old Highway 47 (Scoggins Valley to 835 feet south): October 17, 20 – 28
- Scoggins Valley Road (Highway 47 to West Shore): October 17, 20 – 28
- Walker Road (VonNeumann to 185th): April 2015
Updated paving schedule as of August 20:
- Terman Road (Terman to Murray-northbound): September 2 – 3
- Alexander Street (170th to 185th): September 2 – 5
- Alexander Street (185th to 209th): September 8 – 9, 26 & 29 – 30
- Verboort Road (Cornelius-Schefflin to Martin): September 12, 15 – 18
- Farmington Road (209th to 1340 feet east of Highway 219): October 3, 6 – 10, 13 – 14
- Tongue Lane (Highway 219 to Iowa Hill): October 13 – 16
- Old Highway 47 (Scoggins Valley to 835 feet south): October 17, 20 – 28
- Scoggins Valley Road (Highway 47 to West Shore): October 17, 20 – 28
- Walker Road (VonNeumann to 185th): April 2015
Original release:
Paving crews under contract with Washington County's Department of Land Use & Transportation will begin paving work next week on a number of major county roads, starting with Park Way between Marlow and Cedar Hills. The county and its contractor, Baker Rock Resources, will work together to make sure traffic moves as smoothly and safely as possible through this necessary road maintenance work.
The following roads are scheduled to be paved:
- Park Way (Marlow to Cedar Hills): August 11 – 15
- Terman Road (Terman to Murray-northbound): August 26 - 28
- Alexander Street (170th to 185th): September 2 - 4
- Alexander Street (185th to 209th): September 8 – 11
- Verboort Road (Cornelius-Schefflin to Martin): September 10 – 18
- Farmington Road (209th to Hwy 219): September 22 – October 3
- Tongue Lane (Highway 219 to Iowa Hill): October 3 - 9
- Old Highway 47 (Scoggins Valley to 835 feet south): October 10 - 21
- Scoggins Valley Road (Highway 47 to West Shore): October 10 - 21
- Walker Road (VonNeumann to 185th): April 2015
Please note: Dates listed above are approximate and subject to change due to weather or other unforeseeable circumstances. For the latest paving schedule, visit www.wc-roads.com.
Advisory signs will be posted before the work begins. Roads will remain open, but may be limited to one-way traffic controlled by flaggers. Expect up to 15-minute delays. Use alternate routes if possible.
For more information, please contact Kim Haughn, Public Information Officer, at [email protected] or (503) 846-7800.
Washington County and Baker Rock Resources thank you for your patience and careful attention to driving.
Related: 2014-2015 Major Road Paving Maps
Washington County is committed to planning, building and maintaining a great transportation system, ensuring the safety of all roadway users, and operating the county roadway system in a cost-effective and environmentally responsible manner.