We plan to build a new sidewalk along the south side of the street, between Saltzman Road and Murray Road. We will also build ADA-compliant curb ramps.
Learn more at Filbert Street (FY 2020-22 Pedestrian & Biking Improvement Project) Frequently Asked Questions.
Construction start (expected): May 2023
Construction finish (expected): June 2023
Update
6/20/2023: This project is complete.
Funding
Cost: $1.3 million (2020 estimate)
Funding sources:
Prior events and comment opportunities
Online open house: Oct. 16-Nov. 1, 2020
FAQs